Pre-Installation Preparation
1. Gather Tools and Materials
Tools:
Cable strippers/crimpers
Multimeter for continuity testing
Torque wrench (for industrial connectors)
Cable ties and strain relief clamps
Materials:
Shielded machine vision cables (e.g., GigE Vision, CoaXPress, or USB3 Vision)
EMI-resistant conduit (optional)
Anti-static wrist straps
Cable labels for identification

2. Review System Requirements
Confirm the interface standard (e.g., CoaXPress 2.0, USB3 Vision) and maximum cable length per the camera and processor specifications.
Check voltage/power requirements if using Power over Ethernet (PoE) or Power over Coax (PoC).
3. Assess the Environment
Identify sources of electromagnetic interference (EMI) (e.g., motors, power lines).
Plan routes to avoid sharp bends, heat sources, or moving machinery.
Step 1: Power Down and Secure the System
Turn off all connected devices (cameras, processors, robots) to prevent electrical surges.
Disconnect power sources and use lockout/tagout (LOTO) procedures in industrial settings.
Ground yourself with an anti-static wrist strap to avoid electrostatic discharge (ESD) damage.
Step 2: Route the Cable
Avoid High-EMI Zones:
Keep cables ≥30 cm (12 inches) away from motors, inverters, or AC power lines.
Use shielded conduit in environments with heavy interference (e.g., automotive assembly lines).
Maintain Bend Radius:
Follow the manufacturer’s bend radius (typically 10x the cable diameter).
Example: A 6mm-diameter cable should not bend tighter than a 60mm radius.
Secure Cables Properly:
Use nylon cable ties or Velcro straps to fasten cables without over-tightening.
Install strain relief clamps near connectors to prevent tugging.
Step 3: Terminate Connectors
Strip Insulation Carefully:
Use a precision stripper to avoid nicking conductors.
Expose only the necessary conductor length (refer to connector datasheets).
Crimp or Solder Connectors:
For industrial connectors (e.g., M12, BNC), use a torque wrench to ensure proper tightness.
Verify polarity alignment (e.g., pin 1 to pin 1) for multi-conductor cables.
Test Continuity:
Use a multimeter to check for short circuits or open lines before powering up.
Step 4: Grounding and Shielding
Connect Shield Drains:
Attach cable shields to grounded chassis points using pigtail wires or conductive tape.
Ensure grounding paths are low-resistance (<1 ohm).
Terminate Both Ends (for GigE/Coax):
Ground shields at both ends to minimize ground loops in high-noise environments.
Exception: Follow single-point grounding for systems sensitive to ground loops.
Step 5: Verify Signal Integrity
Power Up Gradually:
Reconnect devices one at a time, starting with the processor.
Test Signal Quality:
Use diagnostic software (e.g., GenICam-compatible tools) to check for packet loss or latency.
Inspect live video feeds for artifacts like pixelation or flickering.
Measure EMI Impact:
Use an oscilloscope to compare signal waveforms with/without nearby EMI sources.
Step 6: Finalize and Document
Label Cables:
Tag both ends of each cable with unique IDs (e.g., “Cam01_to_Processor”).
Update System Diagrams:
Document cable routes, lengths, and grounding points for future maintenance.
Conduct a Safety Audit:
Ensure no exposed conductors, sharp edges, or trip hazards.
Common Installation Mistakes to Avoid
Ignoring Bend Radius: Tight bends cause signal loss or cable jacket cracks.
Mixing Cable Types: Using non-shielded cables in high-EMI areas degrades performance.
Poor Grounding: Floating shields invite noise; improper grounding creates loops.
Overlooking Strain Relief: Unsupported connectors lead to premature failure.
Maintenance Tips for Long-Term Reliability
Inspect Quarterly: Check for abrasions, loose connectors, or corrosion.
Clean Connectors: Use isopropyl alcohol and lint-free swabs to remove dust.
Retest After Modifications: Verify signal integrity if machinery layout changes.